Chapter 16: Migration Timeline & Deliverables


Chapter Overview

Target: Complete migration within 2 weeks after Betasky receives a complete, correct migration zip from your agency.

If the zip is missing files, has wrong formats, or fails validation — the clock pauses until you send a fixed package. Archive PDF upload on care orders continues after go-live at your own pace (Chapter 14).


16.1 How delivery works

  1. Kickoff — Betasky sends folder structure and Chapter 5 checklist
  2. You export from Axxess (Report Center lists, Profile PDFs, Med Profile PDFs, etc.)
  3. You pack everything in one zip and send via secure transfer
  4. Betasky reviews the zip — completeness check before import starts
  5. 2-week migration window begins when the zip is accepted
  6. Go-live after your admin completes Chapter 6 verification

One zip, one handoff. Do not send files in scattered emails or partial drops — that delays the timeline.


16.2 Two-week timeline (after zip accepted)

WhenWhat happensWho
Day 1–2Zip review + care order working session (if needed) → approved care order CSVBetasky + your admin
Day 2–5Validation import (dry run) + summary reportBetasky
Day 3–7You fix any gaps; re-send zip supplement if neededYour agency
Day 5–10Final Production import (setup → staff → patients → care orders → meds)Betasky
Day 10–12Your admin runs Chapter 6 verification checklistYour agency
Day 12–14Go-live sign-off + staff training / hypercareBoth

Exact days flex with agency size. ~2 weeks is the goal when the zip is clean.


16.3 When it takes longer than 2 weeks

Timeline extends if:

  • Zip is incomplete (missing Patient List, Employee List, Profile PDFs, etc.)
  • Zip has wrong files (truncated med PDFs, bad naming, corrupt exports)
  • Care order CSV needs another curation round after validation
  • Agency is slow to respond to validation report
  • Major legacy EMR changes during migration week (cutover freeze broken)

Betasky will tell you exactly what is missing. Send an updated zip (or supplement) and we resume.


16.4 What goes in the migration zip

Pack per Chapter 5 folder structure:

  • setup/ — Employee List, physicians, payers, pharmacies, facilities
  • patients/ — Patient List, Patient Roster, Profile PDFs, Medication Profile PDFs (active)
  • Care order source materials for the joint curation session (cert listings, exports, notes)

Not required in the zip: every Schedule Activity PDF for every historical episode. Those upload after care orders exist — your admin in Betasky, phased over time (Chapter 14).


16.5 Deliverable checklist (your side)

  • Migration zip sent via secure transfer (encrypted link or Betasky onboarding channel)
  • Cutover date and admin contact agreed
  • Care order working session completed (for approved CSV)
  • Chapter 6 verification signed off before go-live
  • Archive PDFs on care orders — ongoing after go-live, not blocking day-one go-live

16.6 Deliverable checklist (Betasky side)

  • Zip completeness review within 2 business days of receipt
  • Validation report before Production write
  • Final import completed within 2-week window (when zip is clean)
  • Staff login invites sent
  • Go-live support during hypercare period

16.7 After go-live: archive PDFs

Uploading OASIS, visit notes, and POC to historical care orders is not part of the 2-week clock. Your admin attaches PDFs in Betasky whenever ready — weeks or months after go-live is normal.